Brick Calculator — bricks, mortar and the bed joint

Brick count from the nominal face module, mortar by the cubic foot, and the bed joint coursing really needs: 5/12 in on modular, not the 3/8 in on the spec.

Brick count is exact arithmetic off the nominal face module and the mortar is not, and the bed joint that closes the coursing is not the 3/8″ printed against the size — this shows all three, and where the industry’s own estimating table contradicts itself.

Quick answer: bricks per square foot and per square metre

BrickNominal face (in)Per ft²Per m²
Modular8 × 2-2/36.7572.66
Engineer Modular8 × 3-1/55.62560.55
Closure Modular8 × 44.548.44
Roman12 × 2664.58
Norman12 × 2-2/34.548.44
Engineer Norman12 × 3-1/53.7540.36
Utility12 × 4332.29
Meridian16 × 42.2524.22

Single wythe, running bond, no waste. A modular brick's nominal face includes its mortar joint, so the count is exact; Standard, Queen and King sizes depend on the joint and are in the calculator. BIA asks for at least 5 % waste.

bed head — — —
The dashed rectangle is the face module — the piece of wall one brick occupies, and the number the count is built on. The solid rectangle is the brick you actually get. The two shaded strips are the joints, drawn to the same scale as everything else.
——
Net wall area—
Brick size — nominal / specified—
Face module → brick per unit area—
Courses—
Bed joint the coursing needs—
Brick — net, then ordered—
Mortar (ft³)—
Collar joint—
Bond correction—
Against BIA Table 4 as published—

What I check on a job

What I check before the brick order. The count is only as good as the area I give it, so I take it off the elevations, not the plan perimeter times the height, and I list every opening I deducted. Deductions flatter a wall that is mostly windows: every jamb, head and sill means cut brick and returns, so on a punched facade I move the waste from the 5 percent minimum to the 10 percent the page offers for corners, returns and cutting. Only the opening itself comes off, so the brick around and below each window is already in the wall count; what the page leaves out is the lintels and sills themselves, and those get their own lines on the take-off. When the brick submittal arrives, I check the specified dimensions on its data sheet against the size I selected here, because a substituted unit changes the count. I ask for the mason's count net of waste and set it beside the net figure this page prints, so we are comparing walls, not allowances.

Sizes, coursing and quantities: Brick Industry Association, Technical Notes 10, Dimensioning and Estimating Brick Masonry, February 2009. Table 1 gives modular sizes, specified dimensions and vertical coursing; Table 2 the non-modular sizes; Table 4 the published brick and mortar quantities; Table 5 the collar joints (3.13 ft³ per 100 sq ft at a 3/8″ joint, 4.17 at 1/2″); Table 6 the bond correction factors. The waste guidance is “at least 5 percent” on brick and “add 15 to 25 percent” on mortar. gobrick.com.

The bed joint. BIA Table 1 footnote 3 says the 3/8″ and 1/2″ figures are “common joint sizes used with length and width dimensions” and that “actual bed joint thicknesses vary based on vertical coursing and actual brick height.” For modular brick the vertical module does the deciding: three courses equal 8″, so the bed joint is (8 − 3 × 2-1/4) ÷ 3 = 5/12″, about 10.6 mm. CMHA (formerly NCMA) TEK 05-12, Modular Layout of Concrete Masonry, states the same 5/12″ bed joint and calls it within allowable mortar joint tolerances. It is not 7/16″: that is the nearest sixteenth, and it grows the wall by 1/16″ every three courses. TMS 602, Specification for Masonry Structures, allows ±1/8″ on a bed joint, which is why a 5/12″ target and a 3/8″ call-out both pass inspection. Only the coursing tells you which one you actually got.

6.75, not 6.86. The nominal face is 8″ × 2-2/3″ = 21.33 in², so 144 ÷ 21.33 = 6.75 brick per square foot. That is exactly what BIA Table 4 prints as 675 per 100 sq ft. The 6.86 that circulates is 144 ÷ (8 × 2-5/8), the 3/8″ bed joint again. It turns up even in one manufacturer’s own consumer brochure, whose technical sheet says 6.75. On 1,000 sq ft of wall that is a 107-brick spread.

Tolerance: ASTM C216, Standard Specification for Facing Brick, Table 3, Column A. Type FBS may vary from the specified dimension by ±3/32″ up to 3″, ±1/8″ over 3 to 4″, ±3/16″ over 4 to 6″, ±1/4″ over 6 to 8″, ±5/16″ over 8 to 12″ and ±3/8″ over 12 to 16″. Type FBX is tighter. C216 Note 12 points at ASTM E835/E835M for the list of modular sizes and warns that brick names denoting sizes are regional.

Metric sizes: metric modular 190 × 90 × 57 mm coursing three to 200 mm is from Brampton Brick’s metric modular coursing chart; UK standard format 215 × 102.5 × 65 mm with a 10 mm joint (a 225 × 75 mm module, four courses to 300 mm) is the Brick Development Association format. Neither appears in BIA Table 4, so their quantities here are derived from the geometry above and nothing else. TN 10 warns on its first page that brick for metric projects runs on a 100 mm module and that its own inch-to-millimetre equivalents should not be carried across to metric modular work.

What is not in the table: masons often quote eight bags of masonry cement per 1000 modular brick. BIA prints that rule and in the next sentence calls it a very rough estimate containing an unspecified amount of waste, so it is not used here. Nor are ties, flashing, weeps, lintels, sills, reinforcement or cleanouts. Mortar quantities assume full bed joints on solid units, coring up to 25 percent; hollow units laid with face-shell bedding use roughly 25 to 35 percent less.

Worked example

A 30 × 10 ft veneer wall in modular brick, running bond: how many bricks?

  1. Area = 300 ft².
  2. Modular brick on a 3/8" joint lays at 6.75 per ft² (the nominal 8 × 2-2/3 in face module).
  3. 300 × 6.75 = 2,025 bricks; with the BIA 5% minimum waste, 2,127.

2,025 bricks net, 2,127 to order, in 45 courses. The bed joint that makes 3 courses come to 8 inches is 5/12 in, not the 3/8 in on the spec — the page says so beside the count.

10 values on this page were driven in a browser and compared with independently derived figures on 2026-10-29 (2808 values across 228 calculators site-wide).

Questions

How many modular bricks per square foot?

6.75 on a 3/8-inch joint, from the nominal 8 × 2⅔ inch face. That is 675 bricks per 100 ft² before waste.

Why is the bed joint 5/12 inch and not 3/8?

Because three courses of 2¼-inch modular brick have to come to 8 inches: (8 − 3 × 2.25) ÷ 3 = 0.4167 in. The spec says 3/8; the coursing needs 5/12.

How much mortar does a collar joint take?

3.13 ft³ per 100 sq ft at a 3/8″ joint and 4.17 at 1/2″, from BIA Technical Note 10, Table 5. Choose two wythes and the page adds it to the mortar total, at the 1/2″ figure when the joint is 1/2″ or more.

How much waste should I add to brick and to mortar?

BIA Technical Note 10 says at least 5 percent on brick and 15 to 25 percent on mortar. The page orders brick at the allowance you pick (5%, 10% for corners and returns, 15% for reclaimed or soft brick) and prints mortar as a range, the net volume plus 15 and plus 25 percent.